| Shadd Gas Station Project Information | ||||
|
Get the most recent updates on the Shadd Project Site below. For more information or to speak with someone about this project please call City Hall at (386) 496-3401. View Project Barometer - View the progress of the project which is displayed on the barometer. This file will open in Microsoft Powerpoint. Project Update for 12/13/2012 - Only 15 LDA holes left to complete before we start the main excavation. Our tonnage as of 1/12/12 is 4,878.78 tons. We will not be starting Coastal next week, as FP&L has not yet rerouted the power lines
Project Update for 2/03/2012 - Shadd update - we are currently at
approximately 13,500 tons (50% finished) as of 2/1/12 with just about
the entire excavation dug to 14-15 feet bls. There was a lot of debris
buried in the back part of the site, concrete, pipes, signs, etc. I will
add this to the total and as soon as I find out the how much additional
concrete disposal we need I will send a VCO. |
||||
|
|
||